Society - Urbanism

Dénia finances the asphalting of roads in the Montgó area and the installation of public lighting in the Ginjoler park with funds from the Plan + CERCA 2020 of the Alicante Provincial Council

February 05 from 2021 - 15: 16

The municipal government will present in the extraordinary plenary session that it plans to convene at the end of next week the two projects that it is going to carry out with the aid of the Plan + CERCA 2020 called by the Alicante Provincial Council. The budget for the actions amounts to 287.166 euros, the amount that has corresponded to Dénia within the call.

Image: Aerial view of the Montgó streetAerial view of the Montgó street

The Plan + CERCA 2020 is a project of direct support to municipalities, which gives autonomy to municipalities to decide the destination of subsidies. It has a global amount of 29.848.000 euros and the distribution of the investment in each municipality of the province has been made according to criteria such as the registered population on January 1, 2019, the area in square kilometers, the population density, the population dispersion taking into account the number of districts that make up each municipality and the depopulation in the last 10 years.

One of the projects that the city council will carry out with the help is the paving of roads in the Montgó area whose pavement is in poor condition.

Specifically, it will take place on the Camí Vell Alt from Dénia to Xàbia, between Neptú street and the intersection with Camí Betlems; in the Camí Coll de Pous, where those areas in which the household connections to the sewer system have already been made will be fixed, since it is not anticipated that future works that could damage the asphalt pavement will be carried out; the intersection of Assagador de Cabanes with Dacsa Street, where a mound on the road blocks the passage and there are also remains of defective pavement; Nespra and Flor de la Llimera streets and Camí Alt de Dénia to Xàbia. All roads have lateral areas with vegetation that will be removed prior to the start of the asphalt works.

The term of execution of the works is one month and the global bidding budget amounts to 198.394,24 euros.

On the other hand, the city council is going to provide public lighting in the Ginjoler park with the grant from the + CERCA Plan in order to improve user safety and prevent misuse of the green area. The park has a total area of ​​13.688 square meters divided into two areas and in addition to vegetation, it is equipped with picnic benches and chairs and a playground.

According to the project drawn up by the municipal technicians, the lighting project foresees the installation of 20 LED technology luminaires and 12 projectors or double light points, with two units per column, also LEDs to guarantee the energy efficiency of the installation.

The global budget for the action is 88.771,76 euros and the execution period of the works is two months.