Works for changing the air conditioning Municipal Market will begin on January 9

31 December 2016 - 00: 00

One of the unknowns that had the Association of Municipal Market Vendors has been cleared, since the Dianense Consistory has been informed that on January 9 will begin work on the change of air conditioning in the Municipal Market.

The air appliances will be replaced, the ducts, luminaires and automatic access doors to the premises. In order for these works to be compatible with the daily activity of the vendors and for the safety of themselves and visitors, the space will be divided into two parts. There will be a provisional and partial closure in two phases. This closure will be carried out after the construction of a wall that allows a complete division of the market and avoids accidents and hygienic-sanitary risks of the food.

The term given by the company BECSA, adjudicator of the works, is of 7 weeks, that include of the 9 of January until the 24 of February.

Hall of the Municipal Market of Dénia

Activity calendar in the Municipal Market

9 10 and the January days: The Municipal Market will be closed to the public for the execution of the division of the municipal building.

From 11 to January 27 (first phase): The Municipal Market area will be closed from fishmongers to bars, the second phase, oriented to Calle Carlos, will remain open. Sentí.

The 30 17 January to February (second phase): The second phase of Calle Carlos will be closed Sentí, remaining open the first phase from fishmonger to bar stops inclusive.

20 24 from February to: The Municipal Market will be fully operational, performing the corresponding adjustment tasks.

Dénia City Council apologizes for the inconvenience that can cause these works that are so necessary at the same time as demands by merchants and users.

Stop Dénia Municipal Market