The PP claims that the bars are not installed and the government responds

May 24 from 2018 - 14: 56

Thursday, May 24, and beaches of Dénia they do not have the beach bars. It is the complaint that the councilors of the Party in Dénia, María Mut e Isabel Gallego, have made this morning on the beach. And it is that these infrastructures should have been assembled and in operation since last 1 in May.

According to María Mut, the paperwork for the drafting of the new concessions of the chiringuitos began the 28 in February, when they passed for the first time by the Governing Board. And that was only a few days before it came into force, the January 9, the new contract law. Precisely these specifications indicated that the beach bars had to start operating the 1 in May. But it has not been that way.

The last thing they know from the PP is that on May 7, missing documentation was required from the companies that accessed the concessions, and they assume that until mid-June the beaches of Dénia will not have beach bars.

Óscar Mengual justifies the delay due to the demands of the Contracting Committee

The councilor of beaches in the town hall, the socialist Óscar Mengual explained that the delay is given by a very specific requirement of the Contracting Committee. In order to avoid "collusive practices" On the part of the applicant companies, more documentation has been required to prove that there is no agreement between the interested parties to obtain the best offer.

In this specific case, this request for information started, according to Mengual, from the councilor of the opposition in the Contracting Committee, Sergio Benito (C's). The companies have had ten working days to provide the information, which will be evaluated next Monday.

Mengual has indicated that he is "very calm" because the procedures are meeting the deadlines and expects that in the first weeks of June the beach bars are at full capacity on the entire Dianense coast.

The councilman took the opportunity to explain that the beach beaconing service was put out to tender yesterday and that the company will start installing the beacon in June, a process that can take a week, so they arrive on time for the indicated date , the June 15.