The City of Dénia will present the project to open the Camí La Bota road to the municipal nurseries

August 22 from 2018 - 16: 28

The road opening project that goes from the Camí de la Bota to the lands where the municipal nurseries are located will be exhibited at the Dénia Town Hall. It is an action in a bordering environment between the rural area of ​​western Dénia and the polygon industrial of Madrigueres.

The objective of carrying out this action is to improve accessibility throughout this area, since the connection made with the polygon through the Camí Partida Negrals, is through a single road with double direction of traffic that barely reaches the 3 meters of width. in some of the sections.

Works to realize

Land clearing, including the removal of trees.
Demolition of enclosures.
Dismantling of the greenhouse
Demolitions of interior acequias works.
Earthworks up to platform elevation or esplanade.
Execution of the pluvial collector, including the demolition of the current one.
Execution of the public lighting network.
Execution of the granular base and placement of curbs and rigolas.
Execution of concrete base on sidewalks.
Execution of pavement and sidewalk pavement.
Road signs.

Budget of 172.788 euros

The Bid Base Budget, obtained by applying the Value Added Tax of 21%, amounts to the amount of 172.788,00 €. It is estimated that the duration of the work lasts 3 months.

In the next few days the Official Gazette of the Province of Alicante will publish an advertisement for the project that will be displayed during a period of 20 days that will begin to count from the day after publication.